VittSphere ONE Calculators Blog CA Firm CA Prabhakar Kumar · FCA · ICAI 560762
Case law › ITAT › Saab Technologies B.V. v DCIT (International Taxation), Kolkata
ITATHelps taxpayerNo later treatment foundDTAA art 5DTAA art 5(3)DTAA art 7s.9(1)(i)s.90

Saab Technologies B.V. v DCIT (International Taxation), Kolkata

The Assessing Officer has added together my client's installation contract and the annual maintenance contract that followed it, crossed the treaty's duration threshold, found an installation permanent establishment and attributed 10 per cent of the receipts. Can he aggregate the two contracts?

The Income-tax Act, 1961 was repealed on 1 April 2026. It still governs income earned up to 31 March 2026, and every proceeding about those years however late — assessment, reassessment, rectification, penalty, revision and appeal alike. Income earned from 1 April 2026 is governed by the Income-tax Act, 2025. What changed, and which Act governs your year →

The Assessing Officer has added together my client's installation contract and the annual maintenance contract that followed it, crossed the treaty's duration threshold, found an installation permanent establishment and attributed 10 per cent of the receipts. Can he aggregate the two contracts?

No. The Kolkata Tribunal held that providing annual maintenance services after the project or site has been handed over to the customer is not carrying out installation activities for the purpose of constituting an installation permanent establishment, so that the Assessing Officer's cumulative consideration of the original installation contract and the subsequent maintenance contract was bad in law and the resulting attribution of 10 per cent of the receipts was erroneous. On the duration itself the Tribunal held that the count does not start from the date of signing the contract, and that on the completion certificate and site readiness report the entire transaction was less than six months, so there was no PE under Article 5(3) of the India-Netherlands DTAA.

Decided by the ITAT (Anikesh Banerjee, Judicial Member and Girish Agrawal, Accountant Member) on 2024-04-18, reported as I.T.A. No. 153/KOL/2022, Income Tax Appellate Tribunal, Kolkata 'C' Bench; assessment year 2018-19. The treaty construed is the Double Taxation Avoidance Agreement between INDIA and the NETHERLANDS — Article 5(3), the installation permanent establishment threshold — with attribution under Article 7.. It bears on section DTAA art 5, section DTAA art 5(3), section DTAA art 7, section 9(1)(i), section 90 of the Income Tax Act 1961, in Assessment & Scrutiny and How Tax Law Is Read matters.

Searched for later treatment; none was found. That is not the same as a source affirming it. No later decision applying or doubting this order has been found. There is, however, something a practitioner needs: the assessee was formerly Hitt Holland Institute of Traffic Technology B.V., and the Revenue's appeal against the earlier Kolkata Bench order in its case, ITA No. 104 of 2019 (Commissioner of Income Tax (International Taxation and Transfer Pricing) v Hitt Holland Institute of Traffic Technology B.V., now known as Saab Technologies B.V.), remains pending in the Calcutta High Court; by order of 25 June 2024 it was adjourned to the monthly list of August 2024. That appeal is against the earlier-year order, not this one, so this order is not itself under appeal, but the same question in the same assessee's case is before the High Court and undecided. Two further limits go to how far the order travels. The threshold is treaty-specific: Article 5(3) of the India-Netherlands agreement uses six months, while other Indian treaties use nine or twelve months and some deem a service permanent establishment on a days count instead, so the number has to be taken from the treaty in issue. And the findings here are findings of fact on documents - the completion certificate and the site readiness report - so a project whose documents show a different sequence is untouched by the order. For a year governed by the Income-tax Act 2025 the successor of s.9(1)(i) and of the treaty-override provision in s.90 should be identified before the argument is put; that correspondence has not been established here.

Why it matters

The construction or installation PE is decided by a stopwatch, and the whole dispute is usually about what goes on the clock. This order gives a practitioner three usable rulings on that. First, the start of the clock is not the date the contract was signed — the Tribunal drew that from Cal Dive Marine Construction (Mauritius) Ltd. — so a contract signed months before mobilisation does not begin the count. Second, post-completion annual maintenance does not count towards the installation period; it is a different activity performed after handover, and rolling a separate AMC into the installation contract to cross the threshold is impermissible. Third, the evidence that decides it is documentary: the completion certificate and the site readiness report were what the Tribunal relied on. Two cautions. The threshold is treaty-specific — Article 5(3) of the India-Netherlands treaty is a six-month test, whereas other Indian treaties use nine months or twelve months, and some deem a service PE on a days count instead; take the number from your own treaty. And the order also records day counts of 183 and 180 days alongside the six-month test, so the arithmetic in a given project has to be presented both ways. Finally, note that the attribution consequence followed automatically: with no installation PE, the 10 per cent attribution fell with it.

Binding on the AO and CIT(A) within the Tribunal's jurisdiction. Persuasive elsewhere.

Not yet CA-verified. This entry was found through the sources listed under the Sources tab, and the summary reflects what those sources say. Nobody has yet read the full judgment and signed it off. Check the source before relying on it.

Read aloud by your device. Press again to stop.

Related

Other authorities on the same sections.
Every authority on the provisions this decision turns on: all 90 on s.90 · all 46 on s.9(1)(i) · all 26 on DTAA art 7

Used in these worked examples

Notice situations where this decision carries one of the steps.
A hundred and eight days on a refinery site, a service permanent establishment asserted under article 5(2)(l), and the whole receipt taxed at forty per centThe officer says my US client's engineers crossed the ninety-day line and has taxed the entire contract receipt as business profits - which limb of article 5 is he actually on, and how much of the receipt can article 7 reach?